Calder Way Project Update June 18, 2026

Dear property owners, business managers, and other stakeholders:

 

The Borough of State College is writing to provide you with the latest updates regarding Phase 2 of the Calder Way Improvement Project.

 

This week, the contractor finished installation of stormwater structures and installed conduit between South Atherton Street and South Burrowes Street. 

 

Early next week, the contractor will finish conduit installation. Final paving, from Cresson Alley to South Atherton Street, is expected to be completed by the middle of the week. Restoration will also continue in several areas.

 

Please remember that projects of this nature are fluid and often change, and they can be impacted by inclement weather. You will be updated in a timely manner about these changes as they are received.

 

The Borough emphasizes that primary communications will be sent via email through the Calder Way Communications list. Weekly updates will be provided on Thursday afternoons, and you may receive more than one update per week as conditions change.

 

There are a couple of ways to stay informed throughout the Calder Way Improvement Project:

 

You can visit https://bit.ly/CalderWay for updates and information about Phase 2. You can also contact me directly at tklienfelter@statecollegepa.us or (814) 680-4468.

 

For assistance after hours, please contact Centre County’s non-emergency line at 1-800-479-0050.

 

If you know of anyone who would like to receive the updates, please instruct them to contact me and ask to be added to the Calder Way Improvement Project updates.

 

 

Elton Hayes

Community Engagement Manager/Interim Communications Specialist

Borough of State College

243 South Allen Street

State College, PA 16801

Office: 814-231-3086 ext. 7145

Cell: 814-308-4329